NEW QUESTION 52
Osmotic blistering is most likely to occur as a result of

  • A. applying tine coating too thin.
  • B. overcoating a surface contaminated with chemical salts.
  • C. inadequate anchor pattern/surface profile.
  • D. airless spray application

Answer: D

 

NEW QUESTION 53
Upon arrival of coating materials, the inspector should

  • A. observe aryl document that the applicator WFT at regular intervals during application.
  • B. review coating contractors' plans for storage of coating materials and confirm they meet national, local and owners' fire and environmental regulations.
  • C. observe and document the amount of material and batch numbers.
  • D. observe and document time frame and environmental conditions between each coat.

Answer: C

 

NEW QUESTION 54
Whenever dissimilar metals must join, the most common practice is to

  • A. coat all connected dissimilar metals.
  • B. provide cathodic protection to prevent corrosion,
  • C. avoid coating all connected dissimilar metals.
  • D. provide anodic protection to prevent corrosion.

Answer: A

 

NEW QUESTION 55
When performing tests for oil and grease using an ultra-violet light, the NACE Inspector should be aware that:

  • A. Ultra-Violet light may contaminant the surface
  • B. Chloride salt may produce a false positive
  • C. Synthetic oil or grease may not be identified
  • D. Presence of weld spatter may produce a false positive

Answer: C

 

NEW QUESTION 56
On a blast-cleaned surface, Ian ultraviolet light is generally used to detect

  • A. soluble chemical salts
  • B. sulfates
  • C. inhibitor residues
  • D. grease and oil

Answer: D

 

NEW QUESTION 57
You are the NACE Coating Inspector on an exterior job where the contractor is not using any environmental controls, For the last several hours your reading; indicate the relative humidity is rising and the substrate temperature is dropping. The sky is clouding over and the weather forecast is for evening showers. It is now 4 PM, your readings indicate you have minimally acceptable environmental conditions, however if the current trend continues, you expect to be outside specified conditions soon. The contractor advises you he is going to mix up the next full kit to complete his for the day.
Your FIRST preformed course of action is to:

  • A. Advise the Contractor of your readings
  • B. Advise the Contractor he cannot proceed
  • C. Call your supervisor
  • D. Advise the Contractor he can proceed

Answer: A

 

NEW QUESTION 58
It is good practice for the NACE Inspector to have instrument calibration certificates available:

  • A. Only if the specification requires it
  • B. At all times
  • C. In the field only
  • D. In the office only

Answer: B

 

NEW QUESTION 59
Polymerization is the process of:

  • A. All organic coatings
  • B. All thermoplastic coatings
  • C. Monomers joining together
  • D. Monomers telegraphing

Answer: C

 

NEW QUESTION 60
Non Conformance Reports are completed by the Inspector:

  • A. When the Inspector deems it to be a significant non-conforming item
  • B. In accordance with the specification's definition of a non-conformance
  • C. In every instance that an item does not meet the specification requirements
  • D. When the Inspector and Contractor deem it to be a significant non-conforming item

Answer: D

 

NEW QUESTION 61
If a Thermoset coating is heated it will:

  • A. Soften when heated and retain its softness when cooled
  • B. Harden and return to its original hardness when cooled
  • C. Harden and retain its hardness when cooled
  • D. Soften when heated and return to its original hardness when cooled

Answer: C

 

NEW QUESTION 62
Which one of these elements is not necessary for corrosion to occur:

  • A. Electrolyte
  • B. Cathode
  • C. Anode
  • D. Reference Cell

Answer: D

 

NEW QUESTION 63
Conventional spray is a good choice when:

  • A. High production rates are required
  • B. High quality finishes are required
  • C. High transfer efficiency is required
  • D. High viscosity coatings are being applied

Answer: B

 

NEW QUESTION 64
You are asked to be the only coating inspector on a small bridge recoating job where existing coating contains lead. The owners' representative has supplied you with the local code governing the removal and disposal of lead based coatings, however upon reading the document you having great deal of difficulty understanding the technical language.
As a NACE CIP Level 1 Inspector your preferred course of action is to:

  • A. Hire a third patty to assist you in understanding the document
  • B. Advise the owners' representative of your lack of knowledge in this area
  • C. Carefully review the document and do the best you can
  • D. Minimize your lack of understanding and go ahead with the inspection task to the best of your ability

Answer: C

 

NEW QUESTION 65
Digital hygrometers

  • A. determine relative humidity, air temperature, and dew point temperature:
  • B. use a thermocouple in contact with the surface to measure temperature
  • C. consist of a bimetallic sensing element protected from wind gusts.
  • D. are used to measure temperature from a distance.

Answer: A

 

NEW QUESTION 66
Excessive working of the surface with a power grinder can be detrimental because excessive burnishing

  • A. scratches the surface too deeply resulting in uneven coating application
  • B. develops a good anchor profile resulting in uneven coating application.
  • C. damages structural elements thereby speeding up the corrosion process.
  • D. develops a polished surface, which is a poor anchor profile for most coatings

Answer: D

 

NEW QUESTION 67
When holiday testing is required the Inspector is always required to enforce NACE SP 0188:

  • A. True
  • B. False

Answer: A

 

NEW QUESTION 68
The main responsibilities of the inspector are to

  • A. observe and report the quality of the work performed.
  • B. direct and perform the work stated in the specification.
  • C. demonstrate to the contractor how to apply the coating.
  • D. observe and direct the work of the contractors.

Answer: A

 

NEW QUESTION 69
You are the NACE Inspector on a job where the Owner's specification requites you to perform a twice daily check of blast pressure at the nozzle. It is now day 30 on the job and all of your readings have been within compliance. The Contractor complains that these checks taking up much time and in view of the compliant results they are unnecessary.
Your FIRST preferred course of action is to:

  • A. Skip the checks and just record the same readings as you have been getting
  • B. Keep doing the checks and consult the Owner's representative for direction
  • C. Keep doing the checks regardless
  • D. Skip the checks as you are. confident the blast pressure is OK

Answer: B

 

NEW QUESTION 70
If inspectors identify issues of non-conformance during an inspection, they should

  • A. perform additional tests secretly to ensure there are no other potential issues at the site
  • B. wait until the final report is being prepared to identify the issues in writing so they are fully documented
  • C. instruct the contractor's personnel in how to correct the issue so the project is not delayed
  • D. inform both the Contractor and the inspector's supervisor so they can take appropriate corrective actions

Answer: D

 

NEW QUESTION 71
Due to a previous premature coating failure the owner has required the original coating applicator to return to remove and replace 10,000 square feet of a failed three coat system at the applicator's cost. Due to the financial implications of another failure, the owner has offered you the job as the NACE CIP Level 1 Coating Inspector and explained that he expects you to be his "insurance policy" for this job. You have never been involved in a warranty job before and are unfamiliar with the coating system.
Your preferred FIRST course of action is to:

  • A. Review the Product Data Sheets, and conduct a walk thru of the job site prior to the pre-job Conference
  • B. Review the Product Data Sheets and meet with the Coating Applicator 'prior to the pre-job meeting
  • C. Meet with the owner and explain your limitations and concerns prior accepting the assignment
  • D. Purchase Professional Liability Insurance prior to job commencement

Answer: A

 

NEW QUESTION 72
Which of these tests uses a syringe?

  • A. Potassium ferricyanide
  • B. Sleeve test
  • C. Soluble salts meter
  • D. Bresle patch

Answer: D

 

NEW QUESTION 73
A NACE Coating Inspector is permitted to transport coating material when:

  • A. Asked to do so by the Coating Application team
  • B. The Inspector should never transport coating material
  • C. If the Inspector meets all the necessary requirements for Transportation of Dangerous Goods
  • D. Asked to do so by the Owner's Representative

Answer: B

 