NEW QUESTION 132
Which is a purpose of an End Project Report?
- A. Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed
- B. Identify individuals or groups that need to be told that the project is coming to an end
- C. Review how well the project performed against the Project Initiation Documentation used to authorize it
- D. Ensure that key project information is archived and made secure
Answer: C
NEW QUESTION 133
Which is an objective of the Directing a Project process?
- A. Provide accurate progress information to the Project Manager
- B. Create and authorize the project mandate
- C. Control the day-to-day running of the project
- D. Provide management control and direction
Answer: D
NEW QUESTION 134
Which two roles are linked by the Managing Product Delivery process?
- A. Project Manager and TeamManager
- B. Corporate or programme management and Project Board
- C. Team Manager and external supplier
- D. Project Board and Project Manager
Answer: A
NEW QUESTION 135
According to the 'continued business justification' principle, when is a justifiable reason for a project FIRST needed?
- A. When an organization produces its business plans
- B. Before work to start the project commences
- C. When authorized by the corporate, programme management or the customer
- D. After the executive has been appointed
Answer: B
Explanation:
Explanation/Reference:
Reference: http://prince2.wiki/Continued_business_justification
NEW QUESTION 136
Which is created during the Starting up a Project process?
- A. Project management team role descriptions
- B. Quality Register
- C. Communication Management Strategy
- D. Project mandate
Answer: A
NEW QUESTION 137
Which is a purpose of the 'controlling a stage' process?
- A. To obtain approvals for products delivered in a work package
- B. To select and implement actions that will resolve deviations from a plan within tolerance
- C. To update a project plan to incorporate the actuals from a stage plan
- D. To produce a team plan for the work to be assigned to a team manager
Answer: B
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Controlling_a_Stage#Purpose
NEW QUESTION 138
Which describes a risk event?
- A. The sequence of events and actions that will be put in place if a risk occurs
- B. The achievement of a milestone on the Project Plan
- C. The area of uncertainty in terms of the threat or opportunity
- D. Thederivation or sources of a potential risk to the project
Answer: C
NEW QUESTION 139
Which is a purpose of an End Project Report?
- A. Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed
- B. Identify individuals or groups that need to be told that the project is coming to an end
- C. Review how well the project performed against the Project Initiation Documentation used to authorize it
- D. Ensure that key project information is archived and made secure
Answer: C
Explanation:
Section: Volume B
Explanation/Reference:
NEW QUESTION 140
What is an off-specification?
- A. A major risk
- B. A new requirement
- C. A type of issue
- D. A quality tolerance
Answer: C
NEW QUESTION 141
What should be considered when defining the number of management stages in a project?
- A. When project support will be available
- B. When key decisions need to be made
- C. When the team managers are available
- D. When highlight reports will be submitted
Answer: B
Explanation:
Explanation/Reference:
Reference https://www.prince2primer.com/prince2-management-and-technical-stages/
NEW QUESTION 142
Which is an objective of the 'managing a product delivery' process?
- A. To assess whether the stage products have been approved
- B. To deliver the planned specialist products within tolerance
- C. To request authorization to start the next stage
- D. To ensure the business case is regularly reviewed
Answer: B
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Managing_Product_Delivery#Objective
NEW QUESTION 143
Identify the missing word in the following sentence.
The PRINCE2 method addresses project management with four integrated elements: principles, themes, [ ? ] and tailoring PRINCE2 to the project environment.
- A. products
- B. activities
- C. quality
- D. processes
Answer: D
Explanation:
Explanation
Reference http://www.innolead.co.bw/index.php/inno-content/cid/27/prince2/
NEW QUESTION 144
Which is a purpose of an Exception Plan?
- A. Define the changes which are within the scope of the change budget
- B. Reduce the number of exception assessments, by agreeing a budget to cover the costs of any requests for change
- C. Show the reason for the tolerance deviation from a Stage Plan or Project Plan
- D. Identify the actions required to recover from the effect ofa tolerance deviation
Answer: D
NEW QUESTION 145
What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?
- A. Quality Register
- B. Configuration Item Record
- C. Highlight Report
- D. Checkpoint Report
Answer: D
Explanation:
Section: Volume B
NEW QUESTION 146
Identify the missing words in the following sentence.
Project assurance personnel [ ? ] the project manager.
- A. are able to overturn the decisions of
- B. should support
- C. must be accountable to
- D. report to the project board and
Answer: B
NEW QUESTION 147
Identify the missing word in the following sentence relating to one of the principles:
A PRINCE2 project should have [?] defined for each project objective.
- A. themes
- B. tolerances
- C. principles
- D. processes
Answer: B
Explanation:
Section: Volume B
Explanation
NEW QUESTION 148
Which does NOT reflect the PRINCE2 principle of continued business justification?
- A. The business justification drives decision making
- B. If a project is no longer forecast to deliver a financial benefit, it should be stopped.
- C. There must be a justifiable reason for starting a project
- D. If a project can no longer be justified, it should be stopped
Answer: B
NEW QUESTION 149
Which is NOT confirmed during the Initiating a Project process?
- A. Whether the expected benefits have been achieved
- B. Who will make decisions on any changes during the project
- C. How the management and specialist products of the project should be baselined
- D. How the method will be tailored for the size and complexity ofthe project
Answer: A
NEW QUESTION 150
Which is a responsibility of a risk owner?
- A. Manage, monitor and control all aspects of an assigned risk
- B. Own and authorize the use of the risk budget to fund risk responses
- C. Identify risks to the project that might occur in their department
- D. Determine project risk appetite
Answer: A
NEW QUESTION 151
Which is one of the six aspects of project performance to be managed?
- A. Work
- B. Efficiency
- C. Timescales
- D. Estimate
Answer: C
Explanation:
Explanation
Reference
http://prince2.wiki/Introduction:_The_PRINCE2_Foundation_Training_Manual#Six_variables_.2F_six_perform
NEW QUESTION 152
What is documented in the project plan to support the 'manage by exception' principle?
- A. The project's tolerances for cost and time
- B. A project product's quality criteria
- C. Activities to mitigate project risks
- D. The expected project benefits
Answer: A
NEW QUESTION 153
Which statement about risks is FALSE?
- A. A risk that could have a positive impact on a project's objectives is known as an opportunity
- B. A risk that a project's product is incomplete is known as an off-specification
- C. A risk is an uncertain event that, should it occur, will have an effect on a project's objectives
- D. A risk that could have a negative impact on a project's objectives is known as a threat
Answer: B
NEW QUESTION 154
Which is a minimum requirement for applying the change theme?
- A. To define the project's approach to baselining products
- B. To record every issue that is raised in the issue register
- C. To appoint the project manager as part of the change authority
- D. To establish a change budget to fund changes in scope
Answer: B
Explanation:
Explanation/Reference:
Reference http://prince2.wiki/Themes#Change_Theme
NEW QUESTION 155
......