Free PRINCE2-Practitioner Sample Questions and 100% Cover Real Exam Questions (Updated 285 Questions) [Q102-Q125]

Share

Free PRINCE2-Practitioner Sample Questions and 100% Cover Real Exam Questions (Updated 285 Questions)

Download Real PRINCE2 PRINCE2-Practitioner Exam Dumps Test Engine Exam Questions


PRINCE2 Practitioner exam covers topics such as project planning, risk management, quality control, and stakeholder management. PRINCE2-Practitioner exam consists of 68 multiple choice questions, and a score of 55% is required to pass. PRINCE2-Practitioner exam can be taken online or in person at an accredited testing center.


PRINCE2 Practitioner certification exam is designed to evaluate the understanding and application of the PRINCE2 methodology. PRINCE2-Practitioner exam consists of 68 multiple-choice questions, which are to be completed in 2.5 hours. PRINCE2-Practitioner exam is designed to test the practical understanding of the candidate in various aspects of project management, such as project planning, risk management, and project governance.

 

NEW QUESTION # 102
The 'classroom-based training materials' will be used as the basis for developing the 'e-learning course'. As a result, the executive wants to ensure that the 'classroom-based training materials' are of the required standard.
The executive has asked to meet the project manager every day during stage 2 to discuss progress and identify any concerns regarding quality.
Is this an appropriate approach to applying the organization theme, and why?

  • A. No, because the senior user should be responsible for specifying the quality criteria for the training materials.
  • B. Yes, because the executive should be the key decision-maker on the project, supported by other project board members.
  • C. Yes, because the executive should be available to provide ad hoc direction to the project manager.
  • D. No, because the project manager should be given authority to manage the project on a day-to-day basis.

Answer: D


NEW QUESTION # 103
Project Scenario - Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered.
ABC Company is planning to deliver pilot courses within five months of starting the project.
The ABC Company standard development model for new courses recommends the following stages:

End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.
End of the additional information.
The project's change control approach states that PRINCE2's recommended issue and change control procedure will be used. The senior user has requested that a new set of marketing materials and marketing channels be introduced to support the launch of the training course. The senior user has suggested that this should be managed informally.
Where should the project manager record the issue, and why?

  • A. In the issue register, because this is a request for change requiring a change to a baseline.
  • B. In the daily log, because a change to a product at the default level can be handled informally.
  • C. In the daily log, because the senior user has advised that this change should be informally.
  • D. In the issue register, because issues should be recorded here first, before determining how to manage them.

Answer: D


NEW QUESTION # 104
Scenario
Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.

Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.
Without a Risk Register how can project risks, the progress of risk actions taken to date and the current status of residual risks be measured?

  • A. It was not appropriate to use the Daily Log to capture all risks and issues during the Starting up a Project process. Separate registers should have been set up for risks, issues and lessons learned. This will now be done.
  • B. In a simple project, the Project Initiation Documentation (PID) should contain a register for recording risk information and monitoring project risks throughout the delivery stages. The register will now be added to the PID.
  • C. The Daily Log was correctly used to monitor risks during the Starting up a Project process. It will be used to capture all risks, actions, decisions, assumptions

Answer: C


NEW QUESTION # 105
Scenario
A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff.
This meeting should have occurred by now.
The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.
The contract is to be reviewed and Portraits Ltd reminded of their agreement.
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.
Which 2 statements should be recorded under the Risk management procedure heading?

  • A. Probability will be assessed against the scales defined in this Risk Management Strategy.
  • B. Every threat and opportunity identified must be clearly defined in terms of cause, event and effect.
  • C. 'Reduce' Response actions which result in a lower impact and/or probability rating.
  • D. Any risk which has an expected value of more than £1 k will NOT be registered.
  • E. When a new problem arises, a full impact analysis will be undertaken to assess the impact on the project' objectives and Business Case.

Answer: A,B


NEW QUESTION # 106
HOTSPOT
Scenario:
Techniques, processes and procedures
1. Any threat that may result in a loss of MFH data must be escalated immediately.
Joint agreements
2.Work is to start at the beginning of week 2 (Stage 4).
3.The project will take two years to complete, at an estimated cost of (GBP)2.5m. Tolerances
4.None.
Constraints
5.MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment.
6.Installation work must take place during MFH normal working hours.
7.+(GBP)10,000 / -(GBP)25,000.
Reporting arrangements
8.Highlight Report every Monday by 10.00 am.
9.The report must contain a summary of all products worked on during the previous week.
10.Project Manager must be notified of any issues immediately by telephone.
Problem handling and escalation
11. Impact analysis of all issues must be completed within 24 hours.
Extracts or references
12. The Stage Plan for stage 4 is available from Project Support.
Approval method
13. Project Assurance will review the completed Work Package and confirm completion
Column 1 is a list of actions that occur during the Controlling a Stage process. For each action in Column 1, select from Column 2 the PRINCE2 theme that is being applied. Each selection from Column 2 can be used once, more than once or not at all.
Drop down the answer from column 1 to column 2.

Answer:

Explanation:


NEW QUESTION # 107
This question provides a number of changes which may or may not be required to the Extract from the
Communication Management Strategy provided in the additional information.
Which statement applies to the Timing of communication activities section?

  • A. Delete entry 9 because activities for controlling the project should be planned as part of Project controls in
    the Project Initiation Documentation.
  • B. No change to entry 9 because it describes the timing of performance reports.
  • C. Delete entry 10 because Highlight Reports are a Project Board control, the frequency of which should be
    recorded in the Project controls section of the Project Initiation Documentation.

Answer: B


NEW QUESTION # 108
Product based planning focuses on which of the following:
1.Creating product descriptions
2.Identifying activities
3.Creating a Product hierarchy
4.Creating a Product sequence

  • A. 1, 2, 4
  • B. 2, 3, 4
  • C. 1, 3, 4
  • D. 1, 2, 3

Answer: D


NEW QUESTION # 109
Additional Information

Further information on some resources who could be involved in the project:
Outcome Account Manager: He represents Outcome which is a recruitment agency that provides specialist outsourcing resources. Outcome provided the consultants who carried out the feasibility study and the same consultants will be providing support and guidance to the Information Technology and Facilities teams during the project.
Director of Finance Division: She was transferred from the Information Technology Division 12 months ago. She is responsible for ensuring a cost-conscious approach is adopted in all operational and project activities across the Ministry of Food Hygiene.
Hardware Manager: Reports to the Director of Information Technology. He provides computer hardware to all business functions but has little awareness of the needs of his colleagues working in software.
Payroll Manager: Reports to the Director of Finance. He is a very experienced and efficient qualified accountant who has much of the responsibility of running the Finance Division on behalf of the Director of Finance. He has been involved in drafting the Ministry's business strategy and assisting in a full business risk assessment. He also drafted the corporate Business Case standards.
Which 2 alternative actions apply to the proposed user assurance for this project?

  • A. Remove because neither of these individuals are from the business functions to be outsourced.
  • B. Retain because they are both very positive about outsourcing the selected business functions.
  • C. Retain because their divisions will be the major users of the outsourced services and they can provide the user perspective on the impact of any proposed changes.
  • D. Retain because selecting only one of them may cause unnecessary conflict.
  • E. Retain because they are able to help identify stakeholders and their communication requirements.

Answer: C,E


NEW QUESTION # 110
The change control approach defines how products should be controlled and protected during the project. The accreditation of the 'classroom-based training materials' was planned to take place during stage 2. At the end of the stage, the configuration item record shows that the 'classroom-based training materials' have been accredited. However, the project manager decides to request an audit of the product as well.
Is this appropriate, and why?

  • A. No, because the project manager should ensure that the change control approach is tailored to the project.
  • B. Yes, because the project should verify that the recorded status reflects the actual status of the products.
  • C. No, because the issue management and change control procedures can be treated as separate, but related, procedures.
  • D. Yes, because the change control approach should specify how the configuration item records are approved.

Answer: D


NEW QUESTION # 111
Scenario
A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers' performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered:
Do nothing.
Re-engineer selected business functions.
Outsource selected business functions.
The feasibility study concluded that there was a case for outsourcing the MFH Information Technology Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were:
One service provider should be contracted to provide the services currently provided by the Information Technology Division and the Facilities Division.
A 10-year service contract should be agreed with the selected service provider.
The feasibility study developed high-level designs of the current organization, processes, systems and operating models, plus an outline Business Case for the required project. The external consultants also made the following recommendations for the management of the project:
Use PRINCE2.
Set up the project with 4 management stages:
Stage 1. Standard PRINCE2 initiation activities.
Stage 2. Create detailed designs (future organization, processes, systems and operating models) and the service level agreement between MFH and the future service provider.
Stage 3. Request and evaluate proposals, select service provider and agree contract.
Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run trial period.
Initial estimates indicated that the project would cost £2.5m and take two years to complete.
MFH senior management agreed that there was a case for outsourcing, and accepted the recommendations as a basis for the project. There is an expected saving of £20m over 10 years.
The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage.
Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs.
Which 2 statements should be recorded under the Expected benefits heading?

  • A. The 10-year outsourcing contract will enable MFH to stabilize costs at agreed levels.
  • B. Outsourcing would allow MFH to take advantage of the best services the outsourcing industry has to offer.
  • C. The total expected savings over 10 years, at current prices, is £20m.
  • D. The confirmed cost of the Outsourcing project is £2.5m, but with considerable savings over 10 years.
  • E. The 10-year outsourcing contract, at current prices, will be worth £80m.

Answer: A,C


NEW QUESTION # 112
In the PRINCE2 Quality review technique, who would most likely carry out the role of administrator:

  • A. Team Manager
  • B. Project support
  • C. Project manager
  • D. Project Assurance

Answer: B


NEW QUESTION # 113
What additional risk will this place on the project?

  • A. There is only E70k left in the project change budget.
  • B. None because risks associated with the centralization and rationalization of the Facilities Division will be
    managed by another project.
  • C. The reduced value of the contracted services required by the Outsourcing project may result in an
    insufficient number of proposals being received.
  • D. These changes will delay stage 3 by three weeks.

Answer: B


NEW QUESTION # 114
Which of the following represents the four key characteristics a good Project board should display?

  • A. Authority, Credibility, Commitment, Availability
  • B. Authority, Credibility, Delegation, Availability
  • C. Authority, Credibility, Connections, Delegation
  • D. Authority, Availability, Connections, Delegation

Answer: B


NEW QUESTION # 115
Which of the following roles cannot be combined?

  • A. Senior Suppler and Supplier Assurance
  • B. Project Assurance and Team Manager
  • C. Project Manager and Project Support
  • D. Executive and Senior User

Answer: B

Explanation:
Explanation/Reference:
Testlet 1
Scenario
Additional Information
Product Description

Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.
The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors) Introduction
1. This document defines the approach to be taken to achieve the required quality levels during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status, version and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.


NEW QUESTION # 116
There is no Project Brief. How can there be a common understanding of the desired outcomes for the prepared calendar pack?

  • A. The Project Brief should have been produced and approved before the project progressed into the initiation stage.
  • B. The simple Project Initiation Documentation contains the Quality Management Strategy. This contains details of the acceptance criteria for this project.
  • C. The simple Project Initiation Documentation contains the project definition.

Answer: C


NEW QUESTION # 117
Scenario
Additional Information
Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his visits to the engineering area. As CEO he has an overall perspective of the business strategic requirements and the authority to commit resources as required.
Marketing Director: She has been with the company for three years, following a successful career with a publicity company. She has the ability to represent the needs of the business, particularly as this is a marketing project. She has the authority to commit the annual business marketing budget, from which the project will be funded, as she sees appropriate. She will be responsible for monitoring the expected benefits of the calendar, in particular the improvement of the company's image.
Engineering Manager: He has been responsible for many engineering innovations in the company and is still as keen and energetic as the day he started. VVhilst he will not be part of the project team, his staff will feature in the photos for the promotional calendar.
Central Records: This group of five staff looks after all company records and document control. They now maintain all project files.
Bright Lights: This is the local office supplies company. It supplies all the stationery and office equipment needs of the company and will supply the stationery for this project.
Portraits ltd: This is a professional photographic company with a number of excellent photographers and a history of successful work. This company has been selected to take the photos for the company calendar. It has yet been decided which of the photographers to use.
Which 2 statements explain why the Marketing Director should be appointed as a Senior User for this project?

  • A. She previously had a successful career in publicity.
  • B. A number of the products will be produced by the Sales department and the Marketing department.
  • C. The project will be funded from the business marketing budget.
  • D. She can represent the Marketing department.
  • E. The Marketing department will help to deliver the benefits of this project.

Answer: D,E


NEW QUESTION # 118
Which 2 statements explain why the Sales Manager should be appointed as a Senior User for this project?

  • A. He reports directly to the Marketing Director.
  • B. He joined the company last year with huge enthusiasm.
  • C. He is able to represent current and prospective customer interests.
  • D. The launch of a company calendar will impact the Sales department.
  • E. He would like to move into the Marketing department in the future and sees this as an opportunity to work
    closely with the Marketing Director.

Answer: C,D


NEW QUESTION # 119
When examining a project issue, which three aspects should be considered?
1. Performance targets
2. Business Case
3. Resources
4. Risk

  • A. 2, 3, 4
  • B. 1, 3, 4
  • C. 1, 2, 3
  • D. 1, 2, 4

Answer: D


NEW QUESTION # 120
Who is responsible for reviewing the risk management practices to ensure they are in line with the project's risk management strategy?

  • A. Team Manager
  • B. Project Support
  • C. Project Manager
  • D. Project Assurance

Answer: D

Explanation:
Explanation/Reference:
Testlet 1
Scenario:
The Ministry of Food Hygiene (MFH) has a quality management system which contains a document control process to manage all documentation requirements. The document control process was created by the MFH Quality Manager, who now maintains all of MFH's documents and performs an organization-wide configuration management role. The MFH Quality Manager will administer the configuration management procedure for the Restructuring project since this must comply with the MFH document control process.


NEW QUESTION # 121
Who is responsible for appointing the Project Manager?

  • A. The Executive
  • B. Project Assurance
  • C. Corporate or Programme Management
  • D. The Project Board

Answer: A


NEW QUESTION # 122
Extract from the Project Product Description (with errors)

The information in Column 1 may be entered in the Product Description for the chosen label design. Column 2 is a list of the quality headings (excluding Quality Method) in a Product Description. For each entry in Column
1 decide if it should be included in the Product Description headings shown and select the heading from Column 2 under which it should be recorded.
Drop down the right answer.

Answer:

Explanation:
Explanation


NEW QUESTION # 123
Which 2 statements explain why the CEO should be appointed as the Executive for this project?

  • A. He restricts his visits to the engineering area.
  • B. He has the authority to commit resources as required.
  • C. He knows his job very well.
  • D. He started the company 25 years ago.
  • E. He has an overall perspective of the business's strategic requirements.

Answer: B,E

Explanation:
Explanation


NEW QUESTION # 124
Scenario
A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers' performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered:
● Do nothing.
● Re-engineer selected business functions.
● Outsource selected business functions.
The feasibility study concluded that there was a case for outsourcing the MFH Information Technology Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were:
● One service provider should be contracted to provide the services currently provided by the Information Technology Division and the Facilities Division.
● A 10-year service contract should be agreed with the selected service provider.
The feasibility study developed high-level designs of the current organization, processes, systems and operating models, plus an outline Business Case for the required project. The external consultants also made the following recommendations for the management of the project:
● Use PRINCE2.
● Set up the project with 4 management stages:
Stage 1. Standard PRINCE2 initiation activities.
Stage 2. Create detailed designs (future organization, processes, systems and operating models) and the service level agreement between MFH and the future service provider.
Stage 3. Request and evaluate proposals, select service provider and agree contract.
Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run trial period.
Initial estimates indicated that the project would cost £2.5m and take two years to complete.
MFH senior management agreed that there was a case for outsourcing, and accepted the recommendations as a basis for the project. There is an expected saving of £20m over 10 years.
The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage.
Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs.
Which 2 statements should be recorded under the Expected benefits heading?

  • A. The 10-year outsourcing contract will enable MFH to stabilize costs at agreed levels.
  • B. Outsourcing would allow MFH to take advantage of the best services the outsourcing industry has to offer.
  • C. The total expected savings over 10 years, at current prices, is £20m.
  • D. The confirmed cost of the Outsourcing project is £2.5m, but with considerable savings over 10 years.
  • E. The 10-year outsourcing contract, at current prices, will be worth £80m.

Answer: A,C

Explanation:
Explanation/Reference:
Reference: http://www.whatisprince2.net/prince2-theme-business-case.php


NEW QUESTION # 125
......

New PRINCE2-Practitioner exam dumps Use Updated PRINCE2 Exam: https://www.lead1pass.com/PRINCE2/PRINCE2-Practitioner-practice-exam-dumps.html

Verified PRINCE2-Practitioner Dumps Q&As - PRINCE2-Practitioner Test Engine with Correct Answers: https://drive.google.com/open?id=1z5OJrXKWjalnINpde6E3hznYq3MsLSS9